Pipe insulation off before a plumber reroutes the heating pipes
Example project

- Home
- 1920s two-story house near downtown Antioch, with a full basement and an old boiler
- Original request
- Move two heating pipes so a laundry and a new water heater fit in the basement
- Testing
- Lab test of the pipe wrap and the boiler jacket; both contain asbestos
- Work
- About 40 ft of wrap removed from the runs the plumber will cut; the boiler and its jacket stay
- Timeline
- Lab results in two or three days, then two days of removal
- Estimated cost
- $2,600
Scope of work
A sample of the pipe wrap and the boiler jacket, plastic sheeting and a small enclosure around the runs being cut, glove bags on the fittings, the wrap kept wet and cut away, sealed bags, a HEPA vacuum and wet wipe, and a final check. The rest of the wrap and the boiler jacket stay in place and are left sealed. The plumbing is priced separately.
Project overview
In this example, the owners of one of the older houses near downtown Antioch want a laundry and a new water heater in the basement. Two heating pipes are in the way, and like the rest of the system they are wrapped in thick white insulation. The boiler still heats the house, so it stays.
The wrap and the boiler jacket both test positive. Only the 40 ft of pipe the plumber will cut is stripped, inside plastic, which is under the amount that needs a J#. The rest of the wrap is checked for damage and left alone, and the plumber works on bare pipe.
The goal
The goal is bare, safe pipe where the plumber needs it, with the rest of the system left sealed and on record.
Process
- First visit Samples of the pipe wrap and the boiler jacket go to a lab.
- Before work The runs to be cut are marked with the plumber, and the floor is cleared.
- Day one Plastic and an enclosure go up; glove bags go on the fittings.
- Day two The wrap is wetted, cut off and bagged, the area is vacuumed and wiped, and the plastic comes down.
Planning right
- We do not touch wrap that will stay. Cutting into it makes more dust than leaving it sealed.
- Torn wrap that hangs loose is the part to deal with first, even if no work is planned.
- Give the plumber a copy of the lab report, so the crew knows which runs are clean.
- If the boiler is ever replaced, the jacket and the rest of the wrap come off then, as one job.